- Solar and energy
- Solar inverter
9308
SMA solar inverter event 9308: battery communication fault

Risk level
High
Professional inspection is recommended.
Urgency
High
Quick answer
Event 9308 on an SMA Sunny Tripower Smart Energy hybrid inverter or an SMA Sunny Island battery inverter indicates a communication error in the battery system or a battery management timeout, causing the red error LED to glow.
Safety first
Stop and check this first
- Event 9308 corrective measures are restricted by SMA to a qualified person: never open the inverter or battery enclosure, as lethal DC and AC voltages remain present inside.
- Do not unplug, re-terminate, or bridge the CAN communication cable or Enable/GND lines yourself while the system is energized.
Safe checks you can perform
- Check the red LED on the SMA inverter and read event 9308 on the user interface or Sunny Portal
- Visually verify from the outside whether the battery system is switched on
- Inspect the visible external run of the communication cable without touching terminals
Leave these tasks to a qualified professional
- Do not attempt this professional task: Verify battery power state and inspect the CAN bus cable, Enable/GND lines, and terminators
- Do not attempt this professional task: Check inverter and battery grounding, run the UI communication test, and check battery condition
What a technician must be able to justify
Technician visit
These are the steps they must carry out and show you. Tick them as they work: if steps are skipped, do not accept a part swap.
These are not instructions for opening or handling the equipment yourself. They are the checks that should support a technical conclusion.
Verify battery power state and inspect the CAN bus cable, Enable/GND lines, and terminators
What they doA qualified person ensures that the battery system is switched on and checks the communication wiring: on Sunny Tripower Smart Energy, verifying proper connection of the Enable and GND lines, use of at least Cat 5e twisted-pair cable up to 10 m in length, and 12 mm conductor stripping (or 12 mm bootlace ferrules on multi-core stranded wires); on Sunny Island, checking that the external lithium-ion battery data cable is properly connected and CAN bus terminators are attached.
They must show youthe wiring of the CAN bus conductors, Enable and GND lines, and the installed CAN bus terminators.
In writingthe findings of the battery communication cable inspection and any connector, ferrule, or terminator corrections made.
Check inverter and battery grounding, run the UI communication test, and check battery condition
What they doThe specialist checks that the grounding of the inverter and the battery system is properly installed, runs the communication test via the inverter user interface, and checks the condition of the battery in accordance with the battery manufacturer's documentation.
They must show youthe result of the communication test on the SMA inverter user interface and the red LED turning off.
In writingthe grounding check result, the communication test outcome on the user interface, and the verified condition of the battery system.
Before accepting a part or repair
Nothing has been shown yet. Do not accept a part swap based on the code alone.
Follow these steps
Note: Follow the documented order. An error code identifies the affected system, but it does not prove by itself which part has failed.
Check the red LED on the SMA inverter and read event 9308 on the user interface or Sunny Portal
- Who:
- you, looking at the outside of the inverter and your monitoring portal.
- How:
- check without opening the housing whether the red LED on the inverter is glowing, and open the inverter user interface or Sunny Portal to note the exact timestamp of event 9308.
- Result that matters:
- confirming that battery operation stopped due to event 9308 and saving the timestamp for your technician.
- If the red LED stays lit and event 9308 remains active:
- record the timestamp and proceed to check the outside status of the battery.
- If the red LED turns off and communication recovers on its own:
- keep the log screenshot in case the CAN bus interruption is intermittent.
- Evidence to keep:
- a screenshot from the inverter user interface or Sunny Portal showing event 9308.
Evidence: SMA Sunny Tripower Smart Energy: Event 9308 Battery System Communication Error · SMA Sunny Tripower Smart Energy: LED Signals and Status Display
Visually verify from the outside whether the battery system is switched on
- Who:
- you, inspecting the outside of the battery enclosure.
- How:
- look at the external status LEDs or display on your battery unit without removing any covers or touching power or data cables to see whether the battery is switched on.
- Result that matters:
- knowing whether communication failed because the battery unit is powered off or showing its own alert.
- If the battery is switched off or shows a fault signal on its outside indicator:
- note the battery model and indicator state for your installer.
- If the battery appears powered on normally while event 9308 persists:
- a qualified person must inspect the CAN bus wiring, Enable/GND lines, and grounding.
- Evidence to keep:
- a photo of the external status indicator on the battery unit.
Evidence: SMA Sunny Tripower Smart Energy: Event 9308 Battery System Communication Error
Inspect the visible external run of the communication cable without touching terminals
- Who:
- you, looking at the exposed cable run from the outside.
- How:
- without opening the inverter or battery housing or unplugging connectors, look along the exposed path of the communication cable between the inverter and battery for obvious physical damage.
- Result that matters:
- spotting any external cable damage safely before the technician arrives.
- If you see an externally crushed or severed communication cable:
- leave it untouched and ask your installer to replace the cable.
- If no external damage is visible:
- call a qualified specialist, as SMA restricts event 9308 corrective measures to a qualified person.
- Evidence to keep:
- a photo of the external cable path if any physical damage is visible.
Evidence: SMA Sunny Tripower Smart Energy: Event 9308 Battery System Communication Error · SMA Sunny Island 4.4M / 6.0H / 8.0H Operating Manual: Event Messages
Still not solved
If the error persists, stop here. See what the technician must do and show you.
Where this code applies
A code is meaningful only inside the right product and version context.
Primary scope
- System
- Solar and energy
- Brand
- SMA
- Product type
- Solar inverter
Known code variants
- Battery error 9308
- Battery system communication error 9308
- Error comunicacion sistema bateria 9308
- Event 9308
- Evento 9308
- Fallo de la bateria 9308
- SMA 9308
- Sunny Island 9308
- Sunny Tripower Smart Energy 9308
What it means
In the SMA Sunny Tripower Smart Energy documentation (STP5.0-3SE-40 to STP10.0-3SE-40), event 9308 ('Battery system communication error', marked for Qualified person) indicates that there is a communication error in the battery system. In the SMA Sunny Island operating manual (SI4.4M-13, SI6.0H-13, SI8.0H-13), event 9308 ('Battery error') means the timeout monitoring system of the battery management has triggered. On the inverter, the red LED glows when an error stops operation, and the event message and event number appear on the user interface or in Sunny Portal. An event code alone never proves that the battery or inverter hardware is defective.
Warnings and stop conditions
- Highsource verified
Event 9308 corrective measures are restricted by SMA to a qualified person: never open the inverter or battery enclosure, as lethal DC and AC voltages remain present inside.
Evidence: SMA Sunny Tripower Smart Energy: Event 9308 Battery System Communication Error
- Mediumsource verified
Do not unplug, re-terminate, or bridge the CAN communication cable or Enable/GND lines yourself while the system is energized.
Evidence: SMA Sunny Tripower Smart Energy: Event 9308 Battery System Communication Error · SMA Sunny Island 4.4M / 6.0H / 8.0H Operating Manual: Event Messages
Symptoms and causes
Probable causes · in order
- Battery system switched off or in an internal fault stateCommon
The external battery system is switched off or has entered an internal protection or fault state described in the battery manufacturer's documentation.
Evidence: SMA Sunny Tripower Smart Energy: Event 9308 Battery System Communication Error
- Faulty battery communication cable, CAN bus wiring, Enable/GND lines, or missing CAN terminatorsCommon
The battery communication cable and CAN bus are not wired properly (incorrect connection of Enable and GND lines, cable below Cat 5e twisted-pair specification or exceeding 10 m on Sunny Tripower Smart Energy, or missing CAN bus terminators on Sunny Island).
Evidence: SMA Sunny Tripower Smart Energy: Event 9308 Battery System Communication Error · SMA Sunny Island 4.4M / 6.0H / 8.0H Operating Manual: Event Messages
- Improper grounding of the inverter and the battery systemPossible
The grounding connection of the SMA inverter and the battery system is not properly installed, disrupting reliable communication between the units.
Evidence: SMA Sunny Tripower Smart Energy: Event 9308 Battery System Communication Error
Virtual technician
Does 9308 still appear after these checks?
Answer a few questions to narrow down the likely cause and the safest next action. Guidance only - it never replaces a professional.
Sources and technical references
- 1
SMA Sunny Tripower Smart Energy: Event 9308 Battery System Communication Error
SMA Solar Technology AG · 2026 · official_doc
- 2
SMA Sunny Tripower Smart Energy: Evento 9308 Error comunicacion sistema bateria
SMA Solar Technology AG · 2026 · official_doc
- 3
SMA Sunny Tripower Smart Energy: LED Signals and Status Display
SMA Solar Technology AG · 2026 · official_doc
- 4
SMA Sunny Tripower Smart Energy: Senales de los leds e indicadores de estado
SMA Solar Technology AG · 2026 · official_doc
- 5
SMA Sunny Island 4.4M / 6.0H / 8.0H Operating Manual: Event Messages
SMA Solar Technology AG · 2026 · official_doc
- 6
SMA Sunny Island 4.4M / 6.0H / 8.0H Manual de funcionamiento: Mensajes de evento
SMA Solar Technology AG · 2026 · official_doc
Was this entry useful?