Huawei 2067 solar inverter alarm: faulty power collector

Risk level
Medium
Proceed carefully and stop if the check is unclear.
Urgency
Medium
Quick answer
Huawei alarm 2067 means the inverter has lost communication with the power meter or a CT or PT sensor is disconnected from the meter. Do not open your electrical panel: check whether there was a grid outage and ask your installer to inspect the meter and wiring.
Safety first
Stop and check this first
- The power meter and its CT and PT sensors sit inside the live AC distribution board: never remove panel covers or disconnect a CT while current is flowing, and leave all meter wiring checks to a qualified electrician.
Safe checks you can perform
- Confirm alarm 2067 and its Cause ID in the app
- Check whether the meter display is on or if the grid failed
- Note any recent setting or panel work and call your installer
Leave these tasks to a qualified professional
- Do not attempt this professional task: Meter model, RS485 parameter, cable and power supply verification
- Do not attempt this professional task: CT and PT connection inspection at the power meter
What a technician must be able to justify
Technician visit
These are the steps they must carry out and show you. Tick them as they work: if steps are skipped, do not accept a part swap.
These are not instructions for opening or handling the equipment yourself. They are the checks that should support a technical conclusion.
Meter model, RS485 parameter, cable and power supply verification
What they doFor Cause ID 1, the installer checks that the configured power meter model matches the actual model, that the meter communications parameters match the device RS485 configurations, that the meter is powered on with the RS485 cable properly connected, and that its power supply is not abnormal due to a grid failure.
They must show youthe configured meter model and RS485 parameters alongside the actual meter, plus the meter power supply reading and RS485 cable termination.
In writingthe RS485 settings verified, the meter supply voltage and which cable or parameter was corrected.
CT and PT connection inspection at the power meter
What they doFor Cause IDs 2 and 3, the electrician inspects the distribution board to verify that the current transformer (CT) and, where fitted, the potential transformer (PT) are properly connected to the meter.
They must show youthe CT and PT terminals securely connected at the meter and alarm 2067 cleared.
In writingwhich CT or PT connection was remade and confirmation that meter communication was restored without alarm 2067.
Before accepting a part or repair
Nothing has been shown yet. Do not accept a part swap based on the code alone.
Follow these steps
Note: Follow the documented order. An error code identifies the affected system, but it does not prove by itself which part has failed.
Confirm alarm 2067 and its Cause ID in the app
- Who:
- you, from the monitoring app, without opening the consumer unit or inverter.
- How:
- open the alarm log for code 2067 'Faulty power collector' and note the Cause ID (1, 2 or 3) and the exact time it appeared.
- Result that matters:
- knowing whether Huawei points to power meter communication and supply (Cause 1) or to a CT or PT connection (Causes 2 and 3).
- If Cause ID 1 is shown:
- the installer will need to check the meter power supply, RS485 cable and configured meter settings.
- If Cause ID 2 or 3 is shown:
- the electrician will need to inspect the CT or PT terminations at the meter.
- Evidence to keep:
- a screenshot of alarm 2067 showing the Cause ID and timestamp.
Evidence: Inverter Alarm Reference: 2067 Faulty power collector
Check whether the meter display is on or if the grid failed
- Who:
- you, looking through the window of the electrical panel without removing any cover.
- How:
- Huawei asks whether the power meter is powered on and whether its power supply is abnormal due to a power grid failure; check from outside whether the meter screen is lit and whether your home had a power cut.
- Result that matters:
- spotting whether a grid outage or supply issue left the power meter unpowered.
- If there was a grid failure or the meter display is dark:
- note this down and tell your installer without touching any internal wiring.
- If the meter is lit and grid power is normal:
- an RS485 cable, parameter setting or CT/PT connection issue is more likely.
- Evidence to keep:
- a photo of the meter display through the panel window and notes on any recent power outage.
Evidence: Inverter Alarm Reference: 2067 Faulty power collector
Note any recent setting or panel work and call your installer
- Who:
- you, gathering context for the technician without touching RS485 or CT wires.
- How:
- recall whether anyone changed inverter settings or worked inside the distribution board before alarm 2067 appeared, since Huawei asks to compare the configured meter model and RS485 parameters against the actual device.
- Result that matters:
- helping the installer check the configuration and wiring quickly without anyone opening live enclosures.
- If settings were changed or panel work took place recently:
- pass those details to the installer.
- If nothing was changed before the alarm:
- let them know so they focus on testing the physical RS485, CT and PT connections.
- Evidence to keep:
- a short note of any recent electrical or app configuration changes.
Evidence: Inverter Alarm Reference: 2067 Faulty power collector
Still not solved
If the error persists, stop here. See what the technician must do and show you.
Where this code applies
A code is meaningful only inside the right product and version context.
Primary scope
- System
- Solar and energy
- Brand
- Huawei
- Product type
- Solar inverter
Known code variants
- alarma 2067 Huawei
- contador inteligente Huawei 2067
- Faulty power collector
- Huawei 2067
- Huawei 2067 power meter communication
- Huawei alarm 2067
- Huawei fallo medidor de potencia 2067
- Huawei inverter 2067
- Recolector de energía con fallo
- SUN2000 alarm 2067
- SUN2000 alarma 2067
What it means
In the Huawei Inverter Alarm Reference (EDOC1100345192, updated 2026-07-14), alarm 2067 'Faulty power collector' has severity 'Major'. The reference table gives three Cause IDs for 2067: power meter communication is interrupted (Cause ID 1), the CT is disconnected from the meter (Cause ID 2), or the PT is disconnected from the meter (Cause ID 3). Seeing alarm 2067 alone never proves that the power meter or the inverter itself is defective.
Warnings and stop conditions
- Highsource verified
The power meter and its CT and PT sensors sit inside the live AC distribution board: never remove panel covers or disconnect a CT while current is flowing, and leave all meter wiring checks to a qualified electrician.
Evidence: Inverter Alarm Reference: 2067 Faulty power collector
Symptoms and causes
Probable causes · in order
- Power meter communication interrupted or abnormal meter power supplyCommon
Cause ID 1 in Huawei's reference is that communication with the power meter is interrupted, which can stem from a model or RS485 parameter mismatch, a disconnected RS485 cable, or the meter being unpowered due to a grid failure.
Evidence: Inverter Alarm Reference: 2067 Faulty power collector
- Current transformer (CT) disconnected from the meterPossible
Cause ID 2 states that the current transformer (CT) is disconnected from the power meter.
Evidence: Inverter Alarm Reference: 2067 Faulty power collector
- Potential transformer (PT) disconnected from the meterLess common
Cause ID 3 in Huawei's alarm table is that the potential transformer (PT) is disconnected from the meter.
Evidence: Inverter Alarm Reference: 2067 Faulty power collector
Virtual technician
Does 2067 still appear after these checks?
Answer a few questions to narrow down the likely cause and the safest next action. Guidance only - it never replaces a professional.
Sources and technical references
- 1
Inverter Alarm Reference: 2067 Faulty power collector
Huawei Digital Power · 2026 · official_doc
- 2
Referencia de alarmas del inversor: 2067 Recolector de energía con fallo
Huawei Digital Power · 2026 · official_doc
Was this entry useful?